Position:HomeNewsCompany News

Company News

Pre-approval publicity of “Fumin Baishiya phase one: 30MW ground photovoltaic power plant project of complementation of agricultural cultivation and photovoltaic power generation”

Date:2016-08-15Source:未知Views:times

1. Construction project overview
Project Name: Fumin Baishiya phase one: 30MW ground photovoltaic power plant project of complementation of agricultural cultivation and photovoltaic power generation
Construction site: Kunming, Fumin County, Kuanzhuang Town, Red Eagle Town
Construction unit: Green Energy (Fumin) Solar Technology Co., Ltd
Construction Nature: Newly constructed
Environmental Impact Assessment Unit: Xinjiang Dingyao Engineering Consulting Co., Ltd
Construction content: (1) the newly built 30MW ground photovoltaic power station. The site is located on the hillside, which is within the jurisdiction of the village committee of Yunnan Province Kunming City Fumin County Kuange Town Heping village and Tuozhuo village, including four areas: the first area (Heping west) and the second area (Heping north) are within the jurisdiction of the Heping village committee, the third area (Tuozhuo north) and the fourth area (Tuozhuo south) are within the jurisdiction of the Tuozhuo village committee. The construction adopts open photovoltaic greenhouse square, field collection lines, on-site roads and agricultural planting facilities; (2) the new 110kV Baishiya boost station is located near the Tuozhuo North Area. The construction has building complex, dormitory, power distribution room and main electrical equipment.

2. Public participation
2015.12.21-2015.12.27 made known to the public on the website of Kunming Environmental Engineering Assessment Center
2016.06.08 passed the technical assessment of Kunming Assessment Center

3. Location of EIA documentations
Kunming Environmental Engineering Assessment Center (paper text, electronic text).


4. EIA
The project has passed technology assessment of Kunming environmental engineering assessment center and issued the evaluation opinions "technical impact assessment opinions on the environmental impact report of Fumin Baishiya phase one: 30MW ground photovoltaic power plant project of complementation of agricultural cultivation and photovoltaic power generation" (Kunming EIA opinion No. [2016]92).The project conforms to the national industrial policies, the location of photovoltaic power station is reasonable, the pollution prevention and control measures are feasible, and the pollutant discharge can meet the requirements of discharge standards. The impact of project’s construction on the surrounding environment is in the acceptable range. After carrying out the implementation of the “REPORT” and the pollution control measures from the assessment opinions in accordance with the "three simultaneous", the construction of the project is feasible from the perspective of environmental impact assessment,